Continuous work continues to resolve issues discussed on September 21, 2023 in the city of Evlah at a meeting with representatives of Armenians living in the Karabakh region of the Republic of Azerbaijan.
This was reported by the Administration of the President of Azerbaijan.
It is noted that the next step was ensured by the separation of the city of Hankendi from the Armenian energy system and joining the energy system of Azerbaijan.
“Note that back in 2021 at the Shusha substation built by Azereneri and put into operation with the participation of Azerbaijan President Ilham Aliyev, reserve connectors for Hankendi were installed. Since September 19, 2023, Azereneriy began to install additional supports of high voltage of 110 kV near the Shusha substation and their connection with the Hangkendi line. As a result of the work, the process has already been completed. At the same time, the employees of Azereners and Azerishig checked the distribution networks, protection systems, after which voltage was submitted to the line, ”the administration said.
.