In the areas of Azerbaijan, the construction of new electric networks continues from the Armenian occupation. The press service of Azerishyg OJSC Haqqin.az reported that, according to the relevant instructions of President Ilham Aliyev, OJSC is conducting large-scale work in the Zangilan district, as well as in other liberated territories.
in the framework of the Smart Selo project, implemented in the village of Agaly, to provide the village of electricity, a modern air line of 35 square meters is laid.
Another major project is the power supply of the international airport under construction in Zangilan. A double -circular, completely isolated power line with a voltage of 35 square meters is laid to the airport.
Protective zone (3-6 meters) of a new type of isolated lines of 35 kV by 6-10 times less than existing lines (30-40 meters). If technical losses in existing 35 kV cables are 9-12 percent, then in the isolated cables of the modern type they are 3.5-4 percent. The costs of maintaining networks are reduced from 100 to 30 percent, the annual stock consumption is reduced from 100 to 25 percent, the service period is reduced by 2 times. The amount and duration of accidents in isolated cables is up to 60 percent less than in existing wiring. The duration of planned inputs (network maintenance, repair, prevention, etc.) is 75 percent less than the current lines. The safety of residential and working premises is increased, as well as premises located in the immediate vicinity of high -voltage power lines, the effects of natural disasters on the power line.
is eliminated.
The use of a new type of isolated lines of 35 kV allows you to bring the stability, reliability and efficiency of the country’s energy system to international standards.
At the same time, the possibility of laying such cables in any environment: underground, underwater and air will facilitate the operation of innovative distribution networks of 35/0.4 kV installed in the liberated territories, and will also ensure their stable operation.